Oregon Administrative Rules
Chapter 808 - LANDSCAPE CONTRACTORS BOARD
Division 2 - DEFINITIONS AND STANDARDS
Section 808-002-0280 - Date Work Completed
Current through Register Vol. 63, No. 9, September 1, 2024
(1) Except as provided in subsection (4) of this rule, the phrase "Date Work Completed" means:
(2) The phrase "date work completed" includes the passing of any and all final inspections required by the local building department as to work for which the landscape contracting business:
(3) If a permit was required to be pulled by the landscape contracting business, or the landscape contracting business failed to confirm in writing that necessary permits were obtained by the property owner or general contractor, and any prior inspections were unsuccessful - meaning another final inspection is still required - then the work will not be considered substantially complete.
(4) If no landscape work was performed under the contract, then the phrase "date work completed" refers to whichever of the following events occurred last:
(5) Upon the effective date of the 2023 rule amendments, the provisions of this rule will apply to:
(6) The 2023 amendments to this rule will not apply to claims cases closed prior to the effective date of this rule.
Statutory/Other Authority: ORS 183.325 - 183.410, ORS 670.310 & ORS 671.670
Statutes/Other Implemented: ORS 671.710