(1) Tollway project proposals submitted for consideration under the Oregon Innovative Partnerships Program (ORS 367.800- 367.826) are not subject to OAR 731-040-0050.
(2) When reviewing a proposal from private entities, local or regional governments, the department, or other units of government having an interest in the installation of a tollway to authorize a tollway project, the commission will consider:
(3) Proposers shall address all of the above criteria in each proposal. Proposals shall be submitted to the department, and the department will review each proposal to determine if the proposal is complete. Within 45 days from when the department determines that the proposal is complete, the director will submit the proposal and department comments, if any, to the commission for review.
(4) No tollway project shall be authorized unless the commission finds that either:
(5) After consideration of all of the above factors, the commission, in a duly noticed meeting, may authorize a proposed tollway project for further study, may authorize a proposal for further study subject to conditions that must be met by the proposer, or may refuse to authorize the proposal. The commission's authorization for further study shall not include an application of the state land use goals and shall not be a land use decision.
(6) For a tollway project proposal authorized for further study by the commission under this section, the commission may conduct or cause to be conducted any geological, environmental, land use, engineering or other studies required by law as a condition of construction.
(7) The commission shall not consider authorizing a proposed tollway project for construction until the tollway project has been included as a tollway in the local or regional transportation system plan of jurisdictions in which the project would be located. In addition, the commission must find the proposed project to be consistent with the policies and actions adopted in the Oregon Transportation Plan and the Oregon Highway Plan as of July 19, 2012.
(8) After consideration of the results of any studies undertaken under OAR 731-040-0050(5) and (6) as well as the other factors listed in this rule, the commission, in a duly noticed meeting, may authorize the proposed tollway project for construction, may conditionally authorize the proposed tollway project for construction, or may refuse to authorize the proposed tollway project for construction. After a tollway project is authorized or conditionally authorized for construction, it will be added to the Statewide Transportation Improvement Program.
(9) The commission may refer the proposal or specific components of the proposal to the department for analysis and recommendations at any time before it issues findings;
(10) The commission will issue findings to support its decision to authorize, conditionally authorize or not authorize a tollway project for either further study or construction.
Stat. Auth.: ORS 184.616, 184.619 & 383.015
Stats. Implemented: ORS 383