(1) The grantee must agree to complete the project as approved by the Board and within the timeframe specified in the grant agreement unless proposed modifications are submitted and approved by the Director prior to the beginning of any work proposed in the modification.
(2) The Director may consider project modifications, including expansion of funded projects with moneys remaining from the original project allocation, if the purpose and intent of the amendment remains the same as the original project and the proposed activity is within the same geographic area.
(3) The Director may authorize minor changes within the scope of the original project plan.
(4) The grantee must submit a report at completion of the project in accordance with reporting requirements described in the grant agreement.
(5) Rules and conditions in place at the time funding for the Technical Assistance Grant is formally approved shall govern throughout the term of the project unless changes are mutually agreeable to both parties.
Statutory/Other Authority: ORS 541.984, ORS 541.988, ORS 541.989