Oregon Administrative Rules
Chapter 695 - OREGON WATERSHED ENHANCEMENT BOARD
Division 46 - WATER ACQUISITION GRANTS
Section 695-046-0215 - Director's Funding Approval and Distribution of Funds

Universal Citation: OR Admin Rules 695-046-0215

Current through Register Vol. 63, No. 9, September 1, 2024

(1) The Director may approve the distribution of grant funds when:

(a) The funding conditions, if any, imposed by the Board are met to the full satisfaction of the Director;

(b) The legal and financial terms of the proposed Water Acquisition Project transaction are approved by the Director;

(c) A grant agreement is executed by the Director and the grant applicant; (d) The Director has reconciled conditionally approved funding with actual Water Acquisition Project costs; and

(d) The grant applicant has satisfied the match requirements under 695-046-0190.

(2) For grants established under these rules, the Director is authorized to reimburse the grant applicant for allowable costs identified in OAR 695-046-0185 and to recognize matching contributions under OAR 695-046-0190 that were incurred no earlier than 18 months before the applicable grant application deadline.

(3) Notwithstanding OAR 659-046-0215(1)(a), funds may be distributed prior to Water Acquisition Project transaction closing for due diligence activities specified in OAR 659-046-0185(5) and included in the application budget.

Statutory/Other Authority: ORS 541.906

Statutes/Other Implemented: ORS 541.932(9)

Disclaimer: These regulations may not be the most recent version. Oregon may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.