(1) Upon receipt of a proposed final plan, the Department shall evaluate the plan to determine if it includes the required elements of OAR 690-086-0125 to 690-086-0170 for a Municipal WMCP, OAR 690-086-0225 to 690-086-0270 for a water management and conservation plan submitted by an Agricultural Water Supplier-, or OAR 690-086-0325 to 690-086-0370 for an Alternate Municipal WMCP. The evaluation shall be limited to a review of modifications in the plan and issues that were identified in the Department's written comments provided under OAR 690-086-0910 and, if any deficiencies are identified, the Department's review shall cite the relevant statute or rule.
(2) If the Department determines that the final plan does not include the required elements of OAR 690-086-0120 to 690-086-0170 for a Municipal WMCP, OAR 690-086-0220 to 690-086-0270 for a water management and conservation plan submitted by an Agricultural Water Supplier, or OAR 690-086-0325 to 690-086-0370 for an Alternate Municipal WMCP, the Department shall consult with the water supplier and may provide additional time to correct any discrepancies.
(3) For a Municipal WMCP submitted by a Municipal Water Supplier, the Department shall review the plan to determine if the information and analyses in the plan are sufficient for the Department to make the determination required under OAR 690-086-0130.
(4) For a Municipal WMCP submitted by a Municipal Water Supplier, if the Department determines that the proposed final plan includes the required elements under OAR 690-086-0120 to 690-086-0170 and meets the applicable criteria under OAR 690-086-0130, the Department shall issue a final order approving the plan and notify the water supplier and any person who submitted comments pursuant to 690-086-0905 of the approval. The Department's order shall include the following:
(5) For a water management and conservation plan submitted by an Agricultural Water Supplier, if the Department determines that the proposed final plan satisfies the relevant requirements or if the water supplier satisfactorily corrects any identified discrepancies, the Department shall issue a final order approving the plan and notify the water supplier and any person who submitted comments pursuant to OAR 690-086-0905 of the approval. The Department shall specify in the order approving the plan if an updated plan shall be required and, if so, the date on which the updated plan shall be submitted to the Department. The Department shall not require submittal of an updated plan earlier than five years after issuance of the order approving the plan.
(6) For an Alternate Municipal WMCP submitted by a Small Municipal Water Supplier, the Department shall review the plan to determine if the information and analyses in the plan are sufficient for the Department to make the determination required under OAR 690-086-0330.
(7) For an Alternate Municipal WMCP submitted by a Small Municipal Water Supplier, if the Department determines that the proposed final plan includes the required elements under OAR 690-086-0320 to 690-086-0370 and meets the applicable criteria under OAR 690-086-0330, the Department shall issue a final order approving the plan and notify the water supplier and any person who submitted comments pursuant to OAR 690-086-0905 of the approval. The Department's order shall include the following:
(8) The Department shall issue a final order denying approval of the plan and notify the water supplier and any person who submitted comments pursuant to OAR 690-086-0905 of the issuance of the order if: