Oregon Administrative Rules
Chapter 690 - WATER RESOURCES DEPARTMENT
Division 76 - ESTABLISHMENT OF MINIMUM PERENNIAL STREAMFLOWS
Section 690-076-0025 - Information Base
Current through Register Vol. 63, No. 9, September 1, 2024
(1) The Department and Commission shall consider the following information to the extent available, when evaluating applications:
(2) The Department and Commission may make reasonable assumptions or estimates for information when specific data are not readily available. Any assumptions or estimates used shall be stated for public review and may include but shall not be limited to:
(3) The Commission will determine the adequacy of water supply at a minimum flow location for satisfying existing, planned and potential instream and out-of-stream uses. The Commission will consider the existing streamflow pattern. If there are shortages, the Commission will consider the plans and potential for developing supplies for both instream and out-of-stream needs. The Commission will only consider ground water a separate source if use is not likely to affect streamflow levels and is not in a critical groundwater area. Interbasin transfers may be considered as an additional water supply only if a project has been planned or constructed. The Commission will consider whether planned or potential out-of-stream use could reasonably be served by sources other than natural flow during periods of shortage. If the uses require natural flow, the Commission will evaluate the importance of the planned uses and both the importance and likelihood of potential uses.