Oregon Administrative Rules
Chapter 690 - WATER RESOURCES DEPARTMENT
Division 52 - DECOMMISSIONING RULES FOR NON-FERC PROJECTS
Section 690-052-0020 - Initiation of Decommissioning Process

Universal Citation: OR Admin Rules 690-052-0020

Current through Register Vol. 63, No. 9, September 1, 2024

(1) If an operator does not submit a notice of intent to reauthorize under ORS 543A.030, the Department shall within 60 days after the deadline for filing the Notice of Intent, request from the operator information regarding the decommissioning of the project pursuant to 543A.030(2), if the information has not already been filed. If the Department is unable to contact the operator, the Department may proceed with the decommissioning process, complying with the provisions of this chapter, as practical, in the absence of the operator.

(2) The Department does not have to initiate the decommissioning process upon receipt of the information requested in subsection (1) of this section. However, the Department shall initiate the decommissioning process at least one year prior to the expiration of the project's license.

Stat. Auth.: ORS 536.027, ORS 543A.300(2) & OL 1999, Ch. 873, Sec. 26

Stats. Implemented: ORS 543.092, ORS 543 & ORS 543A

Disclaimer: These regulations may not be the most recent version. Oregon may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.