Oregon Administrative Rules
Chapter 690 - WATER RESOURCES DEPARTMENT
Division 51 - APPROPRIATION AND USE OF WATER FOR HYDROELECTRIC POWER AND STANDARDS FOR HYDROELECTRIC APPLICATIONS
Section 690-051-0400 - Application Filing Fees
Current through Register Vol. 63, No. 9, September 1, 2024
(1) An applicant for a Preliminary Permit or License for a project or for a Permit to appropriate water for power purposes shall pay to the state a project fee based on the capacity of the project to cover costs of recording, publishing notices, conducting the hearing required by ORS 543.225 and making investigations necessary to determine whether a Permit should be granted.
(2) The amount of the total project fee required under section (1) of this rule shall be:
(3) The project fee shall be payable in advance of each of four stages of project review as described in OAR 690 051 0095 as follows:
(4) In addition to the project fee required under this section, any applicant for a project to be sited at a location where anadromous fish or threatened or endangered species are present shall pay a surcharge of 30 percent of the total project fee. The surcharge shall be collected in conjunction with the project fee at each stage of the project review.
Statutory/Other Authority: ORS 536.025, 536.027, 537, 543 & ORS 543.078
Statutes/Other Implemented: ORS 543.078