Oregon Administrative Rules
Chapter 690 - WATER RESOURCES DEPARTMENT
Division 315 - WATER RIGHT PERMIT EXTENSIONS
Section 690-315-0050 - Department Action on Extension Applications
Current through Register Vol. 63, No. 9, September 1, 2024
If the Department finds an applicant has submitted a completed application as required in 690-315-0020 or 690-315-0030, the Department shall process the application as established in this rule.
(1) The Department shall publish notice of the extension application in its weekly public notice prior to issuance of a proposed final order on the extension request. The notice shall include a request for comments on the application, the date by which comments must be received by the Department and information about how an interested person may review or obtain a copy of the application. The comment period shall be at least 30 days. The notice shall also include the following information about the permit and the extension application:
(2) After consideration of the administrative record, including but not limited to any comments filed on the extension application, the Department shall issue a proposed final order granting the extension request, with or without additional conditions, or denying the extension request. The Department is not required to respond directly to comments, but may respond to the issue, if applicable and relevant to the decision, within the proposed final order.
(3) The Department shall send the proposed final order issued under subsection (2) of this rule to the applicant by regular mail, or with the consent of the recipient, by electronic means. The Department shall send a copy of the proposed final order by regular mail to any person other than the applicant who submitted comments and has paid the copy fee required under ORS 536.050. The Department shall also publish notice of the proposed final order in the weekly notice published by the Department.
(4) Permit time extensions may be granted for the reasonable time necessary to complete water development or apply all the water to beneficial use.
(5) Extension orders may include, but are not limited to, any condition or provision needed to:
(6) For extensions exceeding five years, the Department shall establish checkpoints to determine if diligence is being exercised in the development and perfection of the water use permit. Intervals between checkpoints will not exceed five year periods.
Stat. Auth.: ORS 536.025 & 536.027
Stats. Implemented: ORS 536.050, 537.230, 537.248, 537.630 & 539.010