Oregon Administrative Rules
Chapter 690 - WATER RESOURCES DEPARTMENT
Division 200 - WATER SUPPLY WELL CONSTRUCTION STANDARDS: INTRODUCTION, GENERAL STANDARDS, AND DEFINITIONS
Section 690-200-0021 - Special Standards

Universal Citation: OR Admin Rules 690-200-0021

Current through Register Vol. 63, No. 9, September 1, 2024

(1) Site conditions may require specific design, construction, and abandonment procedures to adapt to the existing local geologic and ground water conditions to fully utilize every natural protection to the state's ground water. Specific site conditions may require different design, construction, setback, or abandonment standards than required by the Water Supply Well construction rules. Alternative technologies or methods not addressed in these rules may also exist which could be effectively utilized in the construction or abandonment of a water supply well. Prior to the completion of the well, a bonded constructor must request and receive approval from the Department to use methods or materials that do not meet the water supply well construction standards. The Department may approve such requests either orally or in writing. If oral approval is granted, the written request must be submitted to the Department within three working days of the date of the oral approval. Failure to submit a written request as described above may void the prior oral approval. The proposed methods or materials shall provide at least the same level of resource protection as that which is provided by these rules.

(2) The written request for special standards shall include:

(a) Name, license number and signature of the bonded well constructor;

(b) Location of the well by county, township, range, section, tax-lot (if assigned), 1/4, 1/4 section, and Latitude and Longitude as established by a global positioning system;

(c) Name and address of landowner;

(d) Address of the project/well site;

(e) Type of work;

(f) The distance to the nearest septic tank, drainfield, closed sewage line, and closed storm drainage system;

(g) The reasons(s) that conformance to the rules and regulations for water supply wells cannot be met;

(h) A diagram and written description showing the proposed water supply well design, construction, or abandonment;

(i) A site map showing the relationship of the well to any existing septic tank, drainfield, closed sewage line, and closed storm drainage system, if the request is to place a well within the minimum setbacks described in OAR 690-210-0030;

(j) The well identification number, if assigned;

(k) The start card number; and

(l) Any associated well report numbers if special standard request is for alteration or abandonment.

Statutory/Other Authority: ORS 536.027, ORS 536.090, ORS 537.505-537.795, ORS 536.900 & ORS 537.992

Statutes/Other Implemented: ORS 536.090, ORS 537.505-537.795, ORS 536.900 & ORS 537.992

Disclaimer: These regulations may not be the most recent version. Oregon may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.