Oregon Administrative Rules
Chapter 690 - WATER RESOURCES DEPARTMENT
Division 20 - DAM SAFETY
Section 690-020-0160 - Removal
Current through Register Vol. 63, No. 9, September 1, 2024
(1) Dam owner(s) seeking Removal of any Dam with a High or Significant Hazard Rating must notify the Department.
(2) Dam owner(s) shall provide the Department with a Removal plan for evaluation prior to removing the Dam. Plans must be submitted a minimum of 60 days in advance of Removal to allow reasonable time to evaluate the Removal plan, unless the Department agrees to a different timeframe.
(3) A Removal plan must include:
(4) The Department may evaluate the Removal plan to ensure the plan includes appropriate safety precautions to protect life, property, and public infrastructure from temporary inundation in the area below the Dam during Dam Removal.
(5) The Department may require changes to the Removal plan or require that the work performed under the plan be supervised by an Engineer as necessary to protect life, property, or public infrastructure from temporary inundation during Dam Removal. If the Department requires changes to the Removal plan or requires that work be supervised by an Engineer, the Department shall notify the Dam owner and provide an opportunity to meet with the Department.
(6) Upon completion of the Dam Removal, the owner shall notify the Department. The Department shall make a final inspection, if appropriate, and remove it from Department Dam safety oversight.
Statutory/Other Authority: ORS 536.027, 540.488
Statutes/Other Implemented: ORS 540.452, 540.488