Oregon Administrative Rules
Chapter 690 - WATER RESOURCES DEPARTMENT
Division 20 - DAM SAFETY
Section 690-020-0055 - Design Requirements for New Dams or to Increase Dam Height: Design Drawings
Current through Register Vol. 63, No. 9, September 1, 2024
The Engineer of Record shall submit applicable drawings when the Engineer believes the design is ready for review and approval by the State Engineer.
(1) Drawings must accurately portray the work to be accomplished and be of sufficient detail to clearly define all features of the project. After all changes required by the State Engineer are made, final design drawings must be neatly and accurately drawn to a scale sufficiently large for the drawings to be readily interpreted.
(2) Drawings must be uncluttered and easy to understand for determination of design compliance by the contractor, the Engineer of Record, and the State Engineer.
(3) Drawings must be no larger than 24" X 36". Other acceptable sizes for drawings are 17" X 22" and 22" X 34". All drawings must have a graphic scale bar so that scale can be determined after enlargement or reduction. Each sheet shall be numbered sequentially with the first sheet being sheet number one along with the total number of sheets; e.g., 1 of 6.
(4) Drawings shall include the following information:
(5) Elevations must be clearly labeled on applicable drawings and include the:
(6) All drawings must be dated and have sufficient space for State Engineer's approval stamp, at least 3" x 3" near the lower right hand corner of the drawing.
(7) Drawings must be designated as final design drawings or As-built Drawings.
Statutory/Other Authority: ORS 536.027, 540.488
Statutes/Other Implemented: ORS 540.449, 540.488