Current through Register Vol. 63, No. 9, September 1, 2024
(1) The local government must conduct an evaluation of its plan and land use regulations based on the periodic review conditions in ORS 197.628 and OAR 660-025-0070. The local evaluation process must comply with the following requirements:
(2) The local government must submit the evaluation and work program, or decision that no work program is required, to the department according to the following requirements:
(3) A local government may request an extension of time for submitting its evaluation and work program, or decision that no work program is required. The director may grant the request if the local government shows good cause for the extension. A local government may be permitted only one extension, which shall be for no more than 90 days.
(4) A decision by the director to deny a request for an extension may be appealed to the commission according to the procedures in OAR 660-025-0110(5), or the director may refer a request for extension under section (3) of this rule to the commission pursuant to OAR 660-025-0085.
(5) If a local government fails to submit its evaluation and work program, or decision that no work program is necessary, by the deadline set by the director or the commission, including any extension, the director shall schedule a hearing before the commission according to OAR 660-025-0170(3).
Stat. Auth.: ORS 197.040 & 197.633