(1) Cities and counties shall include a financially-constrained project list in a transportation system plan. Cities and counties shall use the prioritized unconstrained project list developed as provided in OAR 660-012-0170 and the amount of funding available developed as provided in OAR 660-012-0115 to produce the financially-constrained project list.

(2) Cities, counties, Metro, and the state may only develop, fund, and construct projects on the financially-constrained project list.

(a) Cities and counties may only submit projects on the financially-constrained project list in their transportation system plan to the financially-constrained list of a federally-required regional transportation plan.

(b) Cities and counties may develop, fund, or construct a project on the unconstrained project list if:
(A) The project is required as a condition of land development;

(B) A property owner is providing financial or material contributions to the project; and

(C) The project would not require review as provided in OAR 660-012-0830.

(3) Cities and counties shall create a financially-constrained project list using the top available projects on the prioritized unconstrained project list and the planning-level cost estimates developed as provided in OAR 660-012-0170. The sum of the planning-level cost estimates for projects placed on the financially-constrained project list shall not exceed 125 percent of the funding available as identified in OAR 660-012-0115. Cities and counties shall select projects such that the resulting financially-constrained list would:

(a) Reduce per capita vehicle miles traveled, as provided in OAR 660-012-0160;

(b) Burden underserved populations less than and benefit underserved populations as much or more as the city or county population as a whole; and

(c) Make significant progress towards meeting the performance targets set for each performance measure as provided in OAR 660-012-0910 or OAR 660-044-0110.

(4) If the list of projects cannot meet each test in section (3), the city or county must adjust the project list to find the highest-ranking set of projects that can meet the criteria in section (3). This is the financially-constrained project list.

(5) Cities or counties making a major or minor amendment to the transportation system plan as provided in OAR 660-012-0105 which includes an update to any project list, shall update the financially-constrained project list as provided in this rule.

(6) Cities and counties shall prioritize the implementation of projects from the financially-constrained project list for their ability to reduce climate pollution and improve equitable outcomes using the criteria provided in section (3) of this rule.

Statutory/Other Authority: ORS 197.040

Statutes/Other Implemented: ORS 184.899, ORS 197.012, ORS 197.712 & ORS 468A.205

Disclaimer: These regulations may not be the most recent version. Oregon may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.