Oregon Administrative Rules
Chapter 632 - DEPARTMENT OF GEOLOGY AND MINERAL INDUSTRIES
Division 37 - CONSOLIDATED PERMITTING OF MINING OPERATIONS
Section 632-037-0100 - Cooperating Agency Action on a Consolidated Application

Universal Citation: OR Admin Rules 632-037-0100

Current through Register Vol. 63, No. 9, September 1, 2024

(1) At least 30 days before the issuance of draft permits, each cooperating agency shall submit to the Department:

(a) Written concurrence or non-concurrence with the terms and conditions of the draft operating permit as such pertain to the statutory authority of each cooperating agency; and

(b) Permit conditions within the expertise and authority of the cooperating agency.

(2) The Department shall not issue a draft permit until each cooperating agency has concurred with the terms and conditions of the draft permit as such pertain to the statutory responsibility of each cooperating agency.

(3) The Department shall include permit conditions submitted by a cooperating agency as conditions on the Department's draft operating permit.

(4) If the Department finds that a proposed permit condition imposed by a cooperating agency creates a conflict between permits, the technical review team shall resolve the conflict.

Stat. Auth.: ORS 517.750 - 517.995

Stats. Implemented: ORS 517.981

Disclaimer: These regulations may not be the most recent version. Oregon may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.