(1) The permittee of a geothermal prospect well must submit a written application for a permit modification to change plans previously approved by the department unless otherwise directed. The application must set forth in detail the proposed work to be completed and the department must approve the application before work begins.
(2) A detailed report of the work accomplished and the methods employed, including all dates and the results of such work, must be filed within 60 days after completion of the work.
Stat. Auth.: ORS 522
Stats. Implemented: ORS 522.305
Disclaimer: These regulations may not be the most recent version. Oregon may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google
Privacy Policy and
Terms of Service apply.