Oregon Administrative Rules
Chapter 629 - DEPARTMENT OF FORESTRY
Division 623 - SHALLOW, RAPIDLY MOVING LANDSLIDES AND PUBLIC SAFETY
Section 629-623-0700 - Written Plans to Evaluate Public Safety Risk
Current through Register Vol. 63, No. 9, September 1, 2024
(1) To allow evaluation of public safety risk and the appropriate methods for reducing this risk, operators shall submit a written plan for all timber harvesting or road construction operations with intermediate or substantial downslope public safety risk as described in OAR 629-623-0300. Written plans shall include:
(2) Operators shall submit a written plan for proposed stream crossing fills constructed across debris torrent-prone streams with substantial or intermediate downslope public safety risk.
(3) Operators shall submit a written plan for proposed waste fill areas within a drainage containing debris torrent-prone streams where there is substantial or intermediate downslope public safety risk.
Stat. Auth.: ORS 527.710(10)
Stats. Implemented: ORS 527.630(5), 527.674 & 527.714