Oregon Administrative Rules
Chapter 629 - DEPARTMENT OF FORESTRY
Division 605 - PLANNING FOREST OPERATIONS
Section 629-605-0175 - Harvest Type 3 Units Exceeding 120 Acres
Current through Register Vol. 63, No. 9, September 1, 2024
(1) The purpose of this rule is to describe the process that operators shall follow to gain approval of a plan for an alternate practice for a harvest type 3 unit that is between 120 and 240 acres in size.
(2) Operators must obtain written approval of a plan for an alternate practice from the State Forester before conducting operations that result in a single harvest type 3 unit, or combinations of harvest type 3 units, that exceed the contiguous 120 acre limit on a single ownership.
(3) For each unit on which a harvest type 3 is proposed to exceed the contiguous 120 acre limit, the plan for an alternate practice shall:
(4) The State Forester shall review the operator's compliance with the Oregon Forest Practices Act and deny approval of the plan for an alternate practice submitted under this rule when the operator has:
(5) Plans for an alternate practice submitted under this rule shall not be subject to appeal under ORS 527.700(3).
(6) Single harvest type 3 units or combinations of harvest type 3 units may not exceed 240 contiguous acres on a single ownership, except when the units have been reforested as described in ORS 527.750(1)(a), (b) and (c).
(7) The harvest type 3 acreage limitations do not apply for conversions or disasters described in ORS 527.740(4) when the operator obtains approval from the State Forester of a plan for an alternate practice before conducting operations.
Stat. Auth.: ORS 527.710, 526.016(4), 527.714 & 527.715
Stats. Implemented: ORS 527.750(5), 527.765, 527.710(3)(a)(D) & 527.670(8)