(4)
Application of "direction and control" test in construction and landscape
industries:
(a) The provisions of this
section apply to:
(A) Architects licensed
under ORS 671.010 to
671.220;
(B) Landscape architects licensed under ORS
671.310 to 671.479;
(C) Landscaping businesses licensed under ORS
671.510 to
671.710;
(D) Engineers licensed under ORS
672.002 to
672.325; and
(E) Construction contractors licensed under
ORS Chapter 701.
(b) A
licensee described in (6)(a), that is paying for the services of a
subcontractor in connection with a construction or landscape project, will not
be considered to be exercising direction or control over the means or manner by
which the subcontractor is performing work when the following circumstances
apply:
(A) The licensee specifies the desired
results of the subcontractor's services by providing plans, drawings, or
specifications that are necessary for the project to be completed.
(B) The licensee specifies the desired
results of the subcontractor's services by specifying the materials, appliances
or plants by type, size, color, quality, manufacturer, grower, or price, which
materials, appliances or plants are necessary for the project to be
completed.
(C) When specified by
the licensee's customer or in a general contract, plans, or drawings and in
order to specify the desired results of the subcontractor's services, the
licensee provides materials, appliances, or plants, including, but not limited
to, roofing materials, framing materials, finishing materials, stoves, ovens,
refrigerators, dishwashers, air conditioning units, heating units, sod and seed
for lawns, shrubs, vines, trees, or nursery stock, which are to be installed by
subcontractors in the performance of their work, and which are necessary for
the project to be completed.
(D)
The licensee provides, but does not require the use of, equipment (such as
scaffolding or fork lifts) at the job site, which equipment is available for
use on that job site only, by all or a significant number of subcontractors
requiring such equipment.
(E) The
licensee has the right to determine, or does determine, in what sequence
subcontractors will perform work on a project, the total amount of time
available for performing the work, or the start or end dates for subcontractors
working on a project.
(F) The
licensee reserves the right to change, or does change, in what sequence
subcontractors will perform work on a project, the total amount of time
available for performing the work, or the start or end dates for subcontractors
working on a project.