Oregon Administrative Rules
Chapter 436 - DEPARTMENT OF CONSUMER AND BUSINESS SERVICES, WORKERS' COMPENSATION DIVISION
Division 170 - INDEPENDENT CONTRACTORS
Section 436-170-0300 - Application of "Direction and Control" Test in Construction and Landscape Industries

Universal Citation: OR Admin Rules 436-170-0300

Current through Register Vol. 63, No. 3, March 1, 2024

(1) The provisions of this section apply to:

(a) Architects licensed under ORS 671.010 to 671.220;

(b) Landscape architects licensed under ORS 671.310 to 671.479;

(c) Landscaping businesses licensed under ORS 671.510 to 671.710;

(d) Engineers licensed under ORS 672.002 to 672.325; and

(e) Construction contractors licensed under ORS Chapter 701.

(2) A licensee described in section (1) that is paying for the services of a subcontractor in connection with a construction or landscape project, will not be considered to be exercising direction or control over the means or manner by which the subcontractor is performing work when the following circumstances apply:

(a) The licensee specifies the desired results of the subcontractor's services by providing plans, drawings, or specifications that are necessary for the project to be completed.

(b) The licensee specifies the desired results of the subcontractor's services by specifying the materials, appliances or plants by type, size, color, quality, manufacturer, grower, or price, which materials, appliances or plants are necessary for the project to be completed.

(c) When specified by the licensee's customer or in a general contract, plans, or drawings and in order to specify the desired results of the subcontractor's services, the licensee provides materials, appliances, or plants, including, but not limited to, roofing materials, framing materials, finishing materials, stoves, ovens, refrigerators, dishwashers, air conditioning units, heating units, sod and seed for lawns, shrubs, vines, trees, or nursery stock, which are to be installed by subcontractors in the performance of their work, and which are necessary for the project to be completed.

(d) The licensee provides, but does not require the use of, equipment (such as scaffolding or fork lifts) at the job site, which equipment is available for use on that job site only, by all or a significant number of subcontractors requiring such equipment.

(e) The licensee has the right to determine, or does determine, in what sequence subcontractors will work on a project, the total amount of time available for performing the work, or the start or end dates for subcontractors working on a project.

(f) The licensee reserves the right to change, or does change, in what sequence subcontractors will work on a project, the total amount of time available for performing the work, or the start or end dates for subcontractors working on a project.

Stat. Auth: ORS 656.726(4), 670.605

Stats. Implemented: ORS 316.162, 670.600

Disclaimer: These regulations may not be the most recent version. Oregon may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.