A day treatment agency must meet all of the following requirements:

(1) A set of plans and specifications for each day treatment facility operated by the day treatment agency must be submitted to the Department and to the State Fire Marshal for approval:

(a) Prior to construction of a new building;

(b) Prior to construction of an addition to an existing building;

(c) Prior to the remodeling, modification, or conversion of a building; and

(d) In support of an application for initial license of a day treatment agency not previously licensed under OAR 419-430-0020 to 419-430-0110.

(2) The required plans must comply with both current Oregon Structural Specialty Codes (see OAR 837-040-0140) and local fire and safety codes.

(3) Plans must be drawn to scale and must specify the estimated date upon which construction, modification, or conversion will be completed.

Statutory/Other Authority: ORS 409.050, ORS 418.240 & ORS 418.005

Statutes/Other Implemented: ORS 418.205 - 418.325

Disclaimer: These regulations may not be the most recent version. Oregon may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.