In the written response required by OAR 345-029-0020(2)(c), the responsible party must include, as a minimum, the following:

(1) Admission or denial of the violation;

(2) If the responsible party admits the violation and can determine suitable corrective action:

(a) The corrective action taken, and results achieved;

(b) Corrective action that the responsible party plans to take to minimize the possibility of recurrence; and

(c) The date by which the responsible party expects to achieve full compliance; and

(3) If the responsible party admits the violation and cannot determine suitable corrective actions within the 30-day or other time period specified in the notice of violation, a preliminary response that includes a date by which the responsible party will submit a final response that includes all information described in section (2).

Statutory/Other Authority: ORS 469.470

Statutes/Other Implemented: ORS 469.085, 469.440 & 469.992

Disclaimer: These regulations may not be the most recent version. Oregon may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.