Oregon Administrative Rules
Chapter 345 - DEPARTMENT OF ENERGY, ENERGY FACILITY SITING COUNCIL
Division 27 - EXPIRATION, AMENDMENT AND TERMINATION OF SITE CERTIFICATES, AND DEPARTMENT OF ENERGY APPROVAL OF GAS STORAGE TESTING PIPELINES
Section 345-027-0351 - Review Processes for Requests for Amendment
Current through Register Vol. 63, No. 9, September 1, 2024
(1) The transfer review process, described in OAR 345-027-0400, applies to the Council's review of a request for amendment to a site certificate to transfer a site certificate.
(2) The type A review process, consisting of OAR 345-027-0359, 345-027-0360, 345-027-0363, 345-027-0365, 345-027-0367, 345-027-0371 and 345-027-0375, is the default review process and applies to the Council's review of a request for amendment proposing a change described in OAR 345-027-0350(2), (3), or (4).
(3) The type B review process, consisting of OAR 345-027-0359, 345-027-0360, 345-027-0363, 345-027-0365, 345-027-0368, 345-027-0372, and 345-027-0375, applies to the Council's review of a request for amendment that the Department or the Council approves for type B review under OAR 345-027-0357.
(4) The type C review process, described in OAR 345-027-0380, applies to the Council's review of a request for amendment that the Department or the Council approves for type C review under OAR 345-027-0380.
(5) The Council may act concurrently on any combination of proposed changes included in a request for amendment. Concurrent proposed changes are subject to the substantive requirements applicable to each respective proposed change and the Council must review all proposed changes through the process with the more procedural steps applicable to any one of the proposed changes.
Statutory/Other Authority: ORS 469.470
Statutes/Other Implemented: ORS 469.405