Oregon Administrative Rules
Chapter 345 - DEPARTMENT OF ENERGY, ENERGY FACILITY SITING COUNCIL
Division 27 - EXPIRATION, AMENDMENT AND TERMINATION OF SITE CERTIFICATES, AND DEPARTMENT OF ENERGY APPROVAL OF GAS STORAGE TESTING PIPELINES
Section 345-027-0350 - Changes Requiring an Amendment
Universal Citation: OR Admin Rules 345-027-0350
Current through Register Vol. 63, No. 9, September 1, 2024
Except for changes allowed under OAR 345-027-0353, an amendment to a site certificate is required to:
(1) Transfer ownership of the facility or the certificate holder as described in OAR 345-027-0400;
(2) Apply later-adopted laws as described in OAR 345-027-0390;
(3) Extend the construction beginning or completion deadline as described in OAR 345-027-0385;
(4) Design, construct, or operate a facility in a manner different from the description in the site certificate, if the proposed change:
(a) Could result in a significant adverse
impact that the Council has not addressed in an earlier order and the impact
affects a resource or interest protected by an applicable law or Council
standard;
(b) Could impair the
certificate holder's ability to comply with a site certificate condition;
or
(c) Could require a new
condition or a change to a condition in the site certificate.
Statutory/Other Authority: ORS 469.470
Statutes/Other Implemented: ORS 469.405
Disclaimer: These regulations may not be the most recent version. Oregon may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.