Oregon Administrative Rules
Chapter 345 - DEPARTMENT OF ENERGY, ENERGY FACILITY SITING COUNCIL
Division 27 - EXPIRATION, AMENDMENT AND TERMINATION OF SITE CERTIFICATES, AND DEPARTMENT OF ENERGY APPROVAL OF GAS STORAGE TESTING PIPELINES
Section 345-027-0220 - Request for Approval
Current through Register Vol. 63, No. 9, September 1, 2024
(1) Before submitting a request for approval to construct, operate and retire a gas storage testing pipeline, the certificate holder must:
(2) After receiving the information described in section (1) of this rule, the Department must confer with the certificate holder about the Council substantive standards and information requirements that might apply to the proposed pipeline and any extraordinary circumstances that might affect the time requirements for completing the approval process. Within 7 days after conferring with the certificate holder, the Department must send a letter to the certificate holder that includes the following:
(3) The certificate holder must submit to the Department a written request for approval to construct, operate and retire a gas storage testing pipeline with the fee required by the fee schedule established under ORS 469.441. The certificate holder must submit two printed copies of the request, and an electronic version of the full request in a non-copy-protected electronic format acceptable to the Department. The certificate holder must provide additional printed copies to the Department upon request and copies or access to copies to any person requesting copies.
(4) In a request for approval, the certificate holder must include:
Statutory/Other Authority: ORS 469.405
Statutes/Other Implemented: ORS 469.405, 469.421 & 469.441