(1) DEQ will review and approve the Seismic Vulnerability Assessments submitted under OAR 340-300-0003 if they meet the requirements of Chapter 99 of Oregon Law 2022 and these rules.
(2) The DEQ will approve Risk Mitigation Implementation Plan if the plan submitted under OAR 340-300-0004 meets the requirements of Chapter 99 of Oregon Law 2022 and these rules and when implemented will minimize the risk to the human health and safety and the environment in the event of ground shaking and secondary effects.
(3) Before DEQ approves a Seismic Vulnerability Assessment or a Risk Mitigation Implementation Plan required under these rules, DEQ may provide a copy of the mitigation plan to the Department of Geology and Mineral Industries, the office of the State Fire Marshal, the Oregon Department of Energy and the local government jurisdictions for review.
(4) Before approving a Risk Mitigation Implementation Plan, DEQ will provide a public notice and initiate a public comment period as follows:
(5) Public hearing
Statutory/Other Authority: ORS 468.020 & SB 1567 (2022)