Oregon Administrative Rules
Chapter 330 - DEPARTMENT OF ENERGY
Division 68 - INSTITUTIONAL BUILDINGS PROGRAM
Section 330-068-0025 - Obligated Measures
Current through Register Vol. 63, No. 9, September 1, 2024
(1) The Department shall contract with an institution for TAS or ECM projects which meet the requirement of OAR 330-068-0020. The Department shall prepare and submit to Bonneville a request in the form of a table for each additional measure or group of measures for which obligations are created which extends past the end of the federal fiscal year. Each such table shall be prepared in accordance with procedures and format provided by Bonneville, and signed by the Department's authorized contracting officer. Upon execution by Bonneville's authorized contracting officer, such table shall become effective as of the date specified therein, provided such table is received by Bonneville on or before a date to be determined annually by Bonneville.
(2) Each table shall contain the following information, as appropriate:
(3) Upon execution by both parties of each table, the institution shall be obligated for the completion of the measure or measures in such table no later that the date certain established by such table, or an extension thereof in accordance with OAR 330-068-0065.
(4) Upon completion of such measure or measures, and the Department's findings of compliance with the procedures of OAR 330-068-0020, the Department shall pay the institution in accordance with OAR 330-068-0090 for such measure or measures not to exceed the amounts specified in such table.
Stat. Auth.: ORS 183 & ORS 469
Stats. Implemented: ORS 469