Oregon Administrative Rules
Chapter 330 - DEPARTMENT OF ENERGY
Division 25 - RESOURCE PLAN
Section 330-025-0015 - Resource Plan Submission Requirement

Universal Citation: OR Admin Rules 330-025-0015

Current through Register Vol. 63, No. 9, September 1, 2024

(1) On or before July 1, 1982, and on or before every April 1 of even numbered years thereafter, each utility shall submit to the Director a resource plan. This plan shall forecast and describe how the utility will meet demand on its Oregon system (or the systems of its members) over a fifteen-year period as determined by EFSC's most recent biennial forecast of demand and supply. This plan will meet the utility forecast requirement contained in ORS 469.070(4) for those years that a resource plan is due.

(2) Utilities do not have to submit a revised plan if and when EFSC revises its biennial forecast in the interim period between the development of consecutive biennial forecasts.

Stat. Auth.: ORS 469

Stats. Implemented: ORS 469.080

Disclaimer: These regulations may not be the most recent version. Oregon may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.