(1) Transit services projects must be completed prior to applying for a final certification. An applicant must submit amendments to preliminary certifications prior to or at the time of submission of the final certification application.
(2) The department will not review applications for final certification received after the expiration of the preliminary certification or without the final review fee.
(3) The applicant must submit the application on the current department-issued form and all sections must be completed.
(4) The department will review the application, and may conduct an inspection, to verify:
(5) If an application for final certification does not include all information needed to complete the final certification review, the department may ask the applicant, in writing, to submit additional information. If the department does not receive the requested information within 30 calendar days of the date of the notice, the department may deny the application for final certification.
(6) The department will notify the applicant, in writing, if the department denies the application during final review. An applicant may submit a written request for reconsideration within 60 days after the department issues a decision on a final certification.
(7) The department will issue a final certification upon verification that performance of the transit services are complete and that the project complies with statute, rules, the relevant Opportunity Announcement, the preliminary certification and any other applicable requirements.
(8) The department will send a written notification to the applicant of its decision whether to issue a final certification within 60 days after the department receives a complete application for final certification. If more than 60 days pass from the date the applicant submits a complete application and the applicant has not received a written decision from the department, then the application is rejected and no further action will be taken. Any time required to provide additional information as provided in OAR 330-225-0100(5) is not included in this 60 day period.