Oregon Administrative Rules
Chapter 330 - DEPARTMENT OF ENERGY
Division 225 - TRANSIT SERVICES ENERGY INCENTIVES PROGRAM
Section 330-225-0070 - Technical Review
Current through Register Vol. 63, No. 9, September 1, 2024
(1) Once the applicant has paid the technical review fee, the department will conduct a technical review of transit services project applications advanced from the completeness review process. If the applicant does not submit the required technical review fee to the department within 21 calendar days of mailing of the notification for technical review, the department may deny the application.
(2) The department will review the information provided in the application against industry standards to determine whether the service will operate as represented by the applicant.
(3) To be eligible the transit services must meet the following requirements:
(4) The department will review transit services costs for eligibility. If a cost is eligible under the agreement that qualifies the applicant as a recipient or sub-recipient, it will be considered a qualifying service cost. The application must document cost by providing a line item budget.
(5) If an application does not include all information needed to complete the technical review, the department may notify the applicant in writing, requesting additional information. If the department does not receive the requested information within 30 calendar days of the date of the notice, the department may deny the application.
(6) The department will notify the applicant in writing if the department denies the application during the technical review.
(7) If the technical review determines that inaccurate information was submitted by the applicant during the allocation of tax credits, the department may reduce the amount of potential tax credit allocated to the applicant.
Stat. Auth.: ORS 469.040 & 469B.347
Stats. Implemented: ORS 469B.320-469B.347, 315.336 & OL 2012 Ch. 45