Oregon Administrative Rules
Chapter 330 - DEPARTMENT OF ENERGY
Division 220 - ALTERNATIVE FUEL VEHICLE INFRASTRUCTURE ENERGY INCENTIVE PROGRAM
Section 330-220-0090 - Amendments to Preliminary Certifications
Current through Register Vol. 63, No. 9, September 1, 2024
(1) Amendments are documentation of changes to the project described in the application for preliminary certification.
(2) An applicant must submit requests for amendments prior to issuance of the final certification.
(3) Failure of an applicant to submit documentation to the department of changes to the project may result in denial of final tax credit certification.
(4) Changes to the project must be documented by the applicant. The applicant must submit an amendment request on the form specified in the Opportunity Announcement along with the required amendment fee, except that:
(5) Undeclared changes found in the application for final certification or through later inspection must be documented by the applicant by submitting an amendment request on the form specified in the Opportunity Announcement with the required amendment fee. Undeclared changes that result in no reduction to the project's capabilities, no reduction to the project's capacity and are within five percent of the stated fuel displacement may be documented by the department through an inspection report or final review and do not require an amendment fee.
(6) When documenting a change, the applicant must demonstrate that the alternative fuel vehicle project, with the proposed change, will continue to meet the requirements of statute, rule and the Opportunity Announcement; be technically feasible; will operate as represented and would remain in operation for at least five years. The applicant has the responsibility to provide an amendment request with complete technical documentation supporting the proposed amendment. The department may deny amendments submitted without such justification.
(7) An amendment may result in a reduction in tax credit, but may not increase the tax credit amount certified in the preliminary certificate.
(8) If an amendment request does not include all information needed to complete the review, the department may provide the applicant a written request for additional information. If the applicant does not provide the requested information to the department within 30 calendar days of the date of the department's written request, the department may deny the amendment request to amend the preliminary certification.
(9) Requests for amendments must include payment of the appropriate fee, unless provided otherwise in this rule.
(10) The department will decide whether to approve the request.
Stat. Auth.: ORS 469.040, 469B.326, 469B.332, 469B.347