Oregon Administrative Rules
Chapter 330 - DEPARTMENT OF ENERGY
Division 160 - ESTABLISH A RENEWABLE ENERGY CERTIFICATE SYSTEM FOR THE OREGON RENEWABLE PORTFOLIO STANDARD (RPS)
Section 330-160-0080 - Thermal Energy from the Generation of Electricity Using Biomass
Current through Register Vol. 63, No. 9, September 1, 2024
(1) T-RECs may be used to comply with the Oregon RPS if they are created in association with the generation of qualifying thermal energy that is generated in a facility that meets the requirements of Section (3) of this rule and generated in a manner that meets the requirements of Section (4) of this rule.
(2) Qualifying thermal energy must be in the form of direct heat, steam, hot water, or other useful thermal form.
(3) Facility Requirements:
(4) Manner of Generation:
(5) Thermal energy may not be used to comply with the Oregon RPS if:
Stat. Auth.: ORS 469.040, 469A.130, OL 2016, Ch. 28
Stats. Implemented: ORS 469A.010 - 469A.025, 469A-130 - 469A.145, OL 2016, Ch. 28