Oregon Administrative Rules
Chapter 330 - DEPARTMENT OF ENERGY
Division 160 - ESTABLISH A RENEWABLE ENERGY CERTIFICATE SYSTEM FOR THE OREGON RENEWABLE PORTFOLIO STANDARD (RPS)
Section 330-160-0060 - Periodic Review of Multiple-fuel facilities

Universal Citation: OR Admin Rules 330-160-0060

Current through Register Vol. 63, No. 9, September 1, 2024

(1) Multiple-fuel facilities are subject every three years to a review of the percentage of the facility's electricity generation that is allocated to RPS-eligible fuels.

(2) The Department will enter into WREGIS an expiration date for a multiple-fuel facility's Oregon RPS certification that is three years from the date the Department completes its review of the percentage of the facility's electricity generation that is allocated to RPS-eligible fuels.

(3) The Department will provide written notice to a generator representative at least 6 months before its multiple-fuel facility's Oregon RPS certification is scheduled to expire.

(4) For a facility to remain RPS-eligible, the generator representative must complete one of the following actions prior to the facility's Oregon RPS certification expiration date:

(a) Sign a form provided by the Department attesting that the physical equipment and operation of the facility has not changed in a manner that would affect the facility's RPS-eligible fuel allocation since that RPS-eligible fuel allocation was established; or

(b) Provide to the Department an updated calculation of the facility's RPS-eligible fuel allocation with supporting documentation requested by the Department.

(5) Within 30 days of receiving the information provided by the generator representative pursuant to subsection (4) of this section, the Department will update WREGIS to extend the multiple-fuel facility's Oregon RPS certification expiration date by three years.

(6) If the Department determines that the percentage of the facility's electricity generation allocated to RPS-eligible fuels has changed from the facility's current RPS certification, the Department will revise the facility's RPS-eligible fuel allocation in WREGIS accordingly and notify the generator representative of the revised fuel allocation in writing.

Stat. Auth.: ORS 469A.130

Stats. Implemented: ORS 469A.130 - 469A.145

Disclaimer: These regulations may not be the most recent version. Oregon may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.