Oregon Administrative Rules
Chapter 330 - DEPARTMENT OF ENERGY
Division 135 - 1.5 PERCENT FOR GREEN ENERGY TECHNOLOGY IN PUBLIC BUILDING CONSTRUCTION CONTRACTS
Section 330-135-0051 - Requirements for Deferral of Expenditures
Current through Register Vol. 63, No. 9, September 1, 2024
(1) If a contracting agency determines, in accordance with OAR 330-135-0045, that it is not appropriate to install green energy technology, energy use efficiency, or woody biomass energy technology at the public building site or green energy technology, energy use efficiency, or woody biomass energy technology away from the public building site, the contracting agency must:
(2) If the contracting agency defers the expenditure, the amount spent on green energy technology, energy use efficiency, or woody biomass energy technology in the next building project must include the deferred expenditure from the current building project plus the 1.5 percent of total contract price for including green energy technology, energy use efficiency, or woody biomass energy technology in the future building project, if required.
(3) Any amount spent on green energy technology, energy use efficiency or woody biomass energy technology in excess of 1.5 percent of the total contract price may not be credited to other current or future projects.
(4) Public improvement contracts for which state funds are not directly or indirectly used are not required to defer funds, however the contracting agency must comply with (1)(b) of this section.
Statutory/Other Authority: ORS 469.040, ORS 279C.528 & OL 2019, Ch. 160 (HB 2496)
Statutes/Other Implemented: ORS 279C.527, ORS 279C.528 & OL 2019, Ch. 160 (HB 2496)