(1) For space or water heating, eligible costs include the cost of the boiler, associated piping, boiler controls, fuel storage bins, fuel delivery system from the storage tank, piping, heat exchangers, de-ashing equipment, pumps, metering, controls, labor, and commissioning. Costs for heat distribution systems, such as ductwork or radiant floors, or costs for backup systems that use conventional energy sources, do not qualify.

(2) For combined heat and power systems, eligible costs include the costs listed in (1) above and costs for power generation equipment.

Statutory/Other Authority: ORS 469.040 & ORS 279C.528

Statutes/Other Implemented: ORS 279C.527 & ORS 279C.528

Disclaimer: These regulations may not be the most recent version. Oregon may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.