(1) Project Location. To be eligible for this GP, the project must be located within the geographic area of Agate-Winlo soils. This area generally conforms to the boundaries of the Agate-Winlo soil map unit as mapped by the Natural Resources Conservation Service's Jackson County soil survey.

(2) Type of Water. This GP authorizes removal-fill activities only in vernal pool wetlands and the following other waters that occur in Agate-Winlo soils:

(a) Ditches or other water conveyance structures constructed solely to drain vernal pool lands;

(b) Roadside ditches that are not part of a stream tributary system;

(c) Channels excavated through uplands for irrigation water and return flows; and

(d) Palustrine emergent wetlands that were historically vernal pool wetlands.

(3) Thresholds. To be eligible, a project must meet both of the following:

(a) Impacts to vernal pool wetlands and other waters must be less than two acres; and

(b) Impacts to VPC must be less than 15 acres.

(4) Mitigation. Mitigation must be accomplished in accordance with OAR 141-093-0200.

Statutory/Other Authority: ORS 196.600 - 196.692 & 196.795 - 196.990

Statutes/Other Implemented: ORS 196.600 - 196.692 & 196.795 - 196.990

Disclaimer: These regulations may not be the most recent version. Oregon may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.