Oregon Administrative Rules
Chapter 141 - DEPARTMENT OF STATE LANDS
Division 89 - ADMINISTRATIVE RULES GOVERNING THE ISSUANCE AND ENFORCEMENT OF GENERAL AUTHORIZATIONS WITHIN WATERS OF THIS STATE
Section 141-089-0640 - Pre-Construction Notification
Current through Register Vol. 63, No. 9, September 1, 2024
Except as provided in OAR 141-089-0820 to 141-089-0835:
(1) Project Notification Required. A complete project notification must be submitted to the Department at least 30 calendar days before starting the project. A complete notification is one that contains all the information required on the form provided by the Department and all required attachments.
(2) Review of the Notification. Within 30 calendar days of receipt, the Department will review the notification for completeness and eligibility, make one of the following determinations and notify the responsible party that:
(3) Timeframe for Resubmittal of Incomplete or Ineligible Notifications. If a revised notification or application is not resubmitted within 120 calendar days of an incompleteness or ineligible determination, the Department will presume that the responsible party does not intend to provide revisions to the notification and may administratively close the file. If the Department closes the file under these circumstances, the Department will retain the application fee. If the Department receives a subsequent notification or application for the same or similar project after a file has been closed, the responsible party must pay any applicable fees for the new notification at time of submission.
(4) Project Implementation. The person submitting the notification may begin the project:
Statutory/Other Authority: ORS 196.600 - 196.692 & 196.795 - 196.990
Statutes/Other Implemented: ORS 196.600 - 196.692 & 196.795 - 196.990