Oregon Administrative Rules
Chapter 141 - DEPARTMENT OF STATE LANDS
Division 122 - RULES FOR GRANTING EASEMENTS ON TRUST LANDS
Section 141-122-0040 - Easement Application Requirements
Current through Register Vol. 63, No. 9, September 1, 2024
(1) Except as provided by OAR 141-122-0010(4) (Purpose and Applicability) and 141-122-0100 (Easements Issued on Common School Forest Land), any person wanting to use state-owned land for any of the purposes described in OAR 141-122-0010(2) and (3) must:
(2) Unless otherwise exempt under the provisions of OAR 141-122-0010(4) (Purpose and Applicability), each individual use of, or development placed on state-owned land must be authorized by a separate easement specifically authorizing only that use or development.
(3) The application fee for all easements is as follows:
(4) A single easement application form may be used to request:
(6) An easement application for a conduit must include a cross-sectional drawing that shows the proposed use and the remaining conduit space available for future use.
(7) A fully completed application must be submitted to the Department at least 90 calendar days prior to the proposed use or placement of a development subject to a term easement on state-owned land, unless otherwise allowed by the Director in writing
(8) A fully completed application must be submitted to the Department at least 120 calendar days prior to the proposed use or placement of a development that is eligible for a permanent easement on state-owned land, unless otherwise allowed by the Director in writing.
(9) Any person holding a valid easement (other than a permanent easement) granted by the Department prior to the adoption of these rules who wants to continue holding the authorized area following the expiration of the easement for a use subject to easement must:
Statutory/Other Authority: ORS 273.045
Statutes/Other Implemented: ORS 273.761, 274.040, 274.720, 376.620, 530.050, 530.490 & 758.010