Oregon Administrative Rules
Chapter 137 - DEPARTMENT OF JUSTICE
Division 49 - MODEL RULES GENERAL PROVISIONS RELATED TO PUBLIC CONTRACTS FOR CONSTRUCTION SERVICES
Section 137-049-0900 - Contract Suspension; Termination Procedures

Universal Citation: OR Admin Rules 137-049-0900

Current through Register Vol. 63, No. 3, March 1, 2024

(1) Suspension of Work. In the event a Contracting Agency suspends performance of Work for any reason considered by the Contracting Agency to be in the public interest other than a labor dispute, the Contractor shall be entitled to a reasonable extension of Contract time, and to reasonable compensation for all costs, including a reasonable allowance for related overhead, incurred by the Contractor as a result of the suspension.

(2) Termination of Contract by mutual agreement for reasons other than default.

(a) Reasons for termination. The parties may agree to terminate the Contract or a divisible portion thereof if:
(A) The Contracting Agency suspends Work under the Contract for any reason considered to be in the public interest (other than a labor dispute, or any judicial proceeding relating to the Work filed to resolve a labor dispute); and

(B) Circumstances or conditions are such that it is impracticable within a reasonable time to proceed with a substantial portion of the Work.

(b) Payment. When a Contract, or any divisible portion thereof, is terminated pursuant to this section (2), the Contracting Agency shall pay the Contractor a reasonable amount of compensation for preparatory Work completed, and for costs and expenses arising out of termination. The Contracting Agency shall also pay for all Work completed, based on the Contract Price. Unless the Work completed is subject to unit or itemized pricing under the Contract, payment shall be calculated based on percent of Contract completed. No claim for loss of anticipated profits will be allowed.

(3) Public interest termination by Contracting Agency. A Contracting Agency may include in its Contracts terms detailing the circumstances under which the Contractor shall be entitled to compensation as a matter of right in the event the Contracting Agency unilaterally terminates the Contract for any reason considered by the Contracting Agency to be in the public interest.

(4) Responsibility for completed Work. Termination of the Contract or a divisible portion thereof pursuant to this rule shall not relieve either the Contractor or its surety of liability for claims arising out of the Work performed.

(5) Remedies cumulative. The Contracting Agency may, at its discretion, avail itself of any or all rights or remedies set forth in these rules, in the Contract, or available at law or in equity.

Stat. Auth.: ORS 279A.065

Stats. Implemented: ORS 279C.650, 279C.655, 279C.660, 279C.665 & 279C.670

Disclaimer: These regulations may not be the most recent version. Oregon may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.