Section 137-049-0900 - Contract Suspension; Termination Procedures
Current through Register Vol. 63, No. 9, September 1, 2024
(1) Suspension of Work. In the event a Contracting Agency suspends performance of Work for any reason considered by the Contracting Agency to be in the public interest other than a labor dispute, the Contractor shall be entitled to a reasonable extension of Contract time, and to reasonable compensation for all costs, including a reasonable allowance for related overhead, incurred by the Contractor as a result of the suspension.
(2) Termination of Contract by mutual agreement for reasons other than default.
(3) Public interest termination by Contracting Agency. A Contracting Agency may include in its Contracts terms detailing the circumstances under which the Contractor shall be entitled to compensation as a matter of right in the event the Contracting Agency unilaterally terminates the Contract for any reason considered by the Contracting Agency to be in the public interest.
(4) Responsibility for completed Work. Termination of the Contract or a divisible portion thereof pursuant to this rule shall not relieve either the Contractor or its surety of liability for claims arising out of the Work performed.
(5) Remedies cumulative. The Contracting Agency may, at its discretion, avail itself of any or all rights or remedies set forth in these rules, in the Contract, or available at law or in equity.
Stat. Auth.: ORS 279A.065
Stats. Implemented: ORS 279C.650, 279C.655, 279C.660, 279C.665 & 279C.670