Current through Register Vol. 63, No. 9, September 1, 2024

(1) Records Maintenance; Access. Contractors and subcontractors shall maintain all fiscal records relating to Contracts in accordance with generally accepted accounting principles ("GAAP"). In addition, Contractors and subcontractors shall maintain all other records necessary to clearly document (i) their performance; and (ii) any claims arising from or relating to their performance under a Public Contract. Contractors and subcontractors shall make all records pertaining to their performance and any claims under a Contract (the books, fiscal records and all other records, hereafter referred to as "Records") accessible to the Contracting Agency at reasonable times and places, whether or not litigation has been filed as to such claims.

(2) Inspection and Audit. A Contracting Agency may, at reasonable times and places, have access to and an opportunity to inspect, examine, copy, and audit the Records of any Person that has submitted cost or pricing data according to the terms of a Contract to the extent that the Records relate to such cost or pricing data. If the Person must provide cost or pricing data under a Contract, the Person shall maintain such Records that relate to the cost or pricing data for 3 years from the date of final payment under the Contract, unless a shorter period is otherwise authorized in Writing.

(3) Records Inspection; Contract Audit. The Contracting Agency, and its authorized representatives, shall be entitled to inspect, examine, copy, and audit any Contractor's or subcontractor's Records, as provided in section 1 of this rule. The Contractor and subcontractor shall maintain the Records and keep the Records accessible and available at reasonable times and places for a minimum period of 3 years from the date of final payment under the Contract or subcontract, as applicable, or until the conclusion of any audit, controversy or litigation arising out of or related to the Contract, whichever date is later, unless a shorter period is otherwise authorized in Writing.

Stat. Auth.: ORS 279A.065

Stats. Implemented: ORS 279A.030, 279C.375, 279C.380 & 279C.440

Disclaimer: These regulations may not be the most recent version. Oregon may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.