(1) Notification of Completion; inspection. The Contractor shall notify the Contracting Agency in Writing when the Contractor considers the Contract Work completed. Within 15 Days of receiving Contractor's notice, the Contracting Agency will inspect the project and project records, and will either accept the Work or notify the Contractor of remaining Work to be performed.

(2) Acknowledgment of acceptance. When the Contracting Agency finds that all Work required under the Contract has been completed satisfactorily, the Contracting Agency shall acknowledge acceptance of the Work in Writing.

Stat. Auth.: ORS 279A.065

Stats. Implemented: ORS 279C.570

Disclaimer: These regulations may not be the most recent version. Oregon may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.