Oregon Administrative Rules
Chapter 137 - DEPARTMENT OF JUSTICE
Division 49 - MODEL RULES GENERAL PROVISIONS RELATED TO PUBLIC CONTRACTS FOR CONSTRUCTION SERVICES
Section 137-049-0810 - Waiver of Delay Damages Against Public Policy

Universal Citation: OR Admin Rules 137-049-0810
Current through Register Vol. 63, No. 9, September 1, 2024

Contracting Agencies shall not place any provision in a Public Improvement Contract purporting to waive, release, or extinguish the rights of a Contractor to damages resulting from a Contracting Agency's unreasonable delay in performing the Contract. However, Contract provisions requiring notice of delay, providing for alternative dispute resolution such as arbitration (where allowable) or mediation, providing other procedures for settling contract disputes, or providing for reasonable liquidated damages, are permissible.

Stat. Auth.: ORS 279A.065

Stats. Implemented: ORS 279C.315

Disclaimer: These regulations may not be the most recent version. Oregon may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.