If the Contractor provided a performance bond, the Contracting Agency may afford the Contractor's surety the opportunity to provide a substitute contractor to complete performance of the Contract. A substitute contractor shall perform all remaining Contract Work and comply with all terms and conditions of the Contract, including the provisions of the performance bond and the payment bond. Such substitute performance does not involve the Award of a new Contract and shall not be subject to the competitive Procurement provisions of ORS Chapter 279C.
Stat. Auth.: ORS 279A.065
Stats. Implemented: ORS 279C.365, 279C.370, 279C.375, 279C.380 & 279C.390
Disclaimer: These regulations may not be the most recent version. Oregon may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google
Privacy Policy and
Terms of Service apply.