Section 137-049-0380 - Bid or Proposal Evaluation Criteria

Universal Citation: OR Admin Rules 137-049-0380

Current through Register Vol. 63, No. 3, March 1, 2024

(1) General. A Public Improvement Contract, if Awarded, must be Awarded to the Responsible Bidder submitting the lowest Responsive Bid, or to the Responsible Proposer submitting the best Responsive Proposal. (See OAR 137-049-0390, and Rules for Alternative Contracting Methods at 137-049-0600 to 137-049-0690.)

(2) Bid Evaluation Criteria. Invitations to Bid may solicit lump-sum Offers, unit-price Offers or a combination of the two.

(a) Lump Sum. If the ITB requires a lump-sum Bid, without additive or deductive alternates, or if the Contracting Agency elects not to award additive or deductive alternates, Bids must be compared on the basis of lump-sum prices, or lump-sum base Bid prices, as applicable. If the ITB calls for a lump-sum base Bid, plus additive or deductive alternates, the total Bid price must be calculated by adding to or deducting from the base Bid those alternates selected by the Contracting Agency, for the purpose of comparing Bids.

(b) Unit Price. If the Bid includes unit pricing for estimated quantities, the total Bid price must be calculated by multiplying the estimated quantities by the unit prices submitted by the Bidder, and adjusting for any additive or deductive alternates selected by the Contracting Agency, for the purpose of comparing Bids. Contracting Agencies shall specify within the Solicitation Document the estimated quantity of the procurement to be used for determination of the low Bidder. In the event of mathematical discrepancies between unit price and any extended price calculations submitted by the Bidder, the unit price governs. (See OAR 137-049-0350(2)(b).)

(3) Proposal Evaluation Criteria. If the Contracting Agency's Contract Review Authority has exempted the Procurement of a Public Improvement from the competitive bidding requirements of ORS 279C.335(1), and has directed the Contracting Agency to use an Alternative Contracting Method under 279C.335(4), the Contracting Agency shall set forth the evaluation criteria in the Solicitation Documents. (See OAR 137-049-0640, 137-049-0650, 137-049-0670, 137-049-0690, ORS 279C.335 and 279C.405.)

Stat. Auth.: ORS 279A.065, OL 2011, ch 458

Stats. Implemented: ORS 279C.335, OL 2011, ch 458

Disclaimer: These regulations may not be the most recent version. Oregon may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.