Oregon Administrative Rules
Chapter 137 - DEPARTMENT OF JUSTICE
Division 49 - MODEL RULES GENERAL PROVISIONS RELATED TO PUBLIC CONTRACTS FOR CONSTRUCTION SERVICES
Section 137-049-0150 - Emergency Contracts; Bidding and Bonding Exemptions

Universal Citation: OR Admin Rules 137-049-0150

Current through Register Vol. 63, No. 3, March 1, 2024

(1) Emergency Declaration. A Contracting Agency may declare that Emergency circumstances exist that require prompt execution of a Public Contract for Emergency construction or repair Work. The declaration shall be made at an administrative level consistent with the Contracting Agency's internal policies, by a Written declaration that describes the circumstances creating the Emergency and the anticipated harm from failure to enter into an Emergency Contract. The Emergency declaration shall be kept on file as a public record.

(2) Competition for Emergency Contracts. Pursuant to ORS 279C.320(1), Emergency Contracts are regulated under ORS 279B.080, which provides that, for an emergency procurement of construction services, the Contracting Agency shall ensure competition that is reasonable and appropriate under the Emergency circumstances, and may include Written requests for Offers, oral requests for Offers or direct appointments without competition in cases of extreme necessity, in whatever solicitation time periods the Contracting Agency considers reasonable in responding to the Emergency.

(3) Emergency Contract Scope. Although no dollar limitation applies to Emergency Contracts, the scope of the Contract must be limited to Work that is necessary and appropriate to remedy the conditions creating the Emergency as described in the declaration.

(4) Emergency Contract Modification. Emergency Contracts may be modified by change order or amendment to address the conditions described in the original declaration or an amended declaration that further describes additional Work necessary and appropriate for related Emergency circumstances.

(5) Excusing Bonds. Pursuant to ORS 279C.380(4) and this rule, the Emergency declaration may also state that the Contracting Agency waives the requirement of furnishing a performance bond and payment bond for the Emergency Contract. After making such an Emergency declaration those bonding requirements are excused for the procurement, but this Emergency declaration does not affect the separate Public Works bond requirement for the benefit of the Bureau of Labor and Industries (BOLI) in enforcing prevailing wage rate and overtime payment requirements. See OAR 137-049-0815 and BOLI rules at OAR 839-025-0015.

Stat. Auth.: ORS 279A.065

Stats. Implemented: ORS 279B.080, 279C.320, 279C.380

Disclaimer: These regulations may not be the most recent version. Oregon may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.