If the proposed investment is subject to approval based on its location inside an SIZ:
(1) A complete Application must also include a locally endorsed and fully executed copy of the SIZ's standardized agreement that unambiguously identifies the Applicant and the proposed investment.
(2) The County may neither negotiate a project-specific agreement nor subject the proposal to approval under discretionary provisions, including but not limited to those under ORS 285C.609.
(3) Material variance between additional requirements established with designation of the SIZ and those found in the agreement submitted by the Applicant shall render such requirements unenforceable.
Stat. Auth.: ORS 285A.075 & 285C.615(7)