(1) The recipient must comply with all applicable state and federal laws, regulations and requirements.

(2) The funding recipient shall follow standard construction practices, such as bonding of engineers and contractors, requiring errors and omissions insurance, performing testing and inspections during construction, and obtaining as-built drawings.

(3) Project materials must include a notation indicating that Business Oregon funding from the Oregon Lottery was used for the project.

(4) For a tide gate construction project the funding recipient shall have a plan for ongoing operation and maintenance that will preserve the project's benefits over its useful life.

Statutory/Other Authority: ORS 285A.075 & Ch 10, OL 2020

Statutes/Other Implemented: Ch 10, OL 2020

Disclaimer: These regulations may not be the most recent version. Oregon may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.