Oregon Administrative Rules
Chapter 123 - OREGON BUSINESS DEVELOPMENT DEPARTMENT
Division 46 - TIDE GATE GRANT AND LOAN PROGRAM
Section 123-046-0030 - Ineligible Project Costs
Universal Citation: OR Admin Rules 123-046-0030
Current through Register Vol. 63, No. 9, September 1, 2024
Tide gate project expenses and costs expressly allowed by OAR 123-046-0020 are eligible for reimbursement from the fund. All other project costs, including but not limited to those listed below, are ineligible for reimbursement:
(1) Cost of purchase of general purpose motor vehicles and other equipment not directly related to the project;
(2) Indirect costs incurred by the applicant or a contractor; and
(3) Project operating or maintenance expenses.
Statutory/Other Authority: ORS 285A.075 & Ch 10, OL 2020
Statutes/Other Implemented: Ch 10, OL 2020
Disclaimer: These regulations may not be the most recent version. Oregon may have more current or accurate information. We make no warranties or guarantees about the accuracy, completeness, or adequacy of the information contained on this site or the information linked to on the state site. Please check official sources.
This site is protected by reCAPTCHA and the Google
Privacy Policy and
Terms of Service apply.