Oregon Administrative Rules
Chapter 123 - OREGON BUSINESS DEVELOPMENT DEPARTMENT
Division 27 - MARINE NAVIGATION IMPROVEMENT FUND
Section 123-027-0056 - Federally Authorized Project Application Requirements
Current through Register Vol. 63, No. 9, September 1, 2024
The Port shall notify the Authority of a potential federally authorized project at the time it initiates the project with the United States Army Corps of Engineers and it shall submit written documentation to the Authority evidencing its participation with the United States Army Corps of Engineers. The written documentation must:
(1) Describe the nature and purpose of the project, including: proposed project scheduling; project term; estimated project cost; the Port's estimated non-federal share of the total project cost; and, the required schedule for payment of the Port's non-federal share of the total project cost;
(2) Contain federal documents that authorize the project, including Reconnaissance/Feasibility Studies; and
(3) Contain a copy of the Port's proposed Local Cost Share Agreement with the United States Army Corps of Engineers for undertaking and carrying out the project.
Stat. Auth.: ORS 285A.075
Stats. Implemented: ORS 777.262 - 777.267